DEPARTMENT OF STATE GROWTH

Midland Highway – South Sections

Completed Aug 2021 to Feb 2024

Project Value $84.5M

shaw contracting - project name and location
TASK

Shaw upgraded 32 km of the Midland Highway near Ross and Oatlands, widening the road to create a safer median and new overtaking lanes. The project included 58 km of wire-rope and guard-rail barriers, 480,000 m² of new seal, reinforced concrete culverts, and bridge interface works. Innovative lime stabilisation improved weak subgrades, reducing truck movements and environmental impact. Careful traffic management and accelerated programming kept the highway open and delivered key sections ahead of schedule. The project’s quality and execution were recognised with a 2024 Civil Contractors Federation (CCF) Tasmania Earth Award.

More Road Construction Projects

  • Midland Highway

    Perth Link Roads

  • East Tamar Highway

    Connector Roundabout