TASWATER

Coolstore Road Pump Station

Completed Mar 2020

Project Value $600K

shaw contracting - project name and location
TASK

Shaw replaced a deteriorating sewer pump station with a new precast structure at Coolstore Road. Deep excavation and constrained conditions required innovative construction methods, including sheet piling and the use of precast components to minimise excavation risk. Despite delays in switchboard supply, the project was completed ahead of schedule with no incidents or disruptions to stakeholders.

More Water Solutions Projects

  • North Esk Irrigation

    Pumps and Pipelines

  • Richmond

    Torrens Street Sewer Pump Station Upgrade